Lock 1 W: 01/11/16 – 02/12/16 Polyurethane resin injection to seal Lock leakage
Lock 8W to 16W: 07/11/16 – 16/12/16 The towpath is also closed
Lock 8W: Replacement of the bottom gates, pointing the Lock chamber
Lock 12W: Gate leakage repairs
Lock 13W: Replacement of the top gate, repairs to the bottom gates, masonry repairs and heel grip repairs
Lock 14W: Replacement of the bottom gates, masonry repairs and heel grip repairs
Lock 16W: Replacement of the bottom gates. masonry and ladder repairs
Lock 22W: 07/11/16 – 16/12/16 The towpath is also closed Replacement of the bottom gates, masonry in and around the lock chamber, ground works around the Lock
Lock 1E to 16E: 07/11/16 – 21/12/16
Lock 9E: Polyurethane resin injection to seal Lock leakage. Gate leakage works, masonry repairs in adjacent pounds
Lock 12E: Gate leakage repairs, brickwork repairs in the Lock chamber
Lock 15E: Polyurethane resin injection to seal the Lock leakage. Gate leakage repairs to the top gate, masonry repairs in and around the Lock chamber
Lock 16E: Polyurethane resin injection to seal the Lock leakage and masonry repairs to the Lock chamber, ground works to the Lock quadrant areas
Lock 18E to 39E: 01/11/16 – 21/12/16 The towpath is also closed
Lock 18E: Polyurethane resin injection to seal the Lock leakage and masonry and ladder repairs within the Lock chamber and leakage repairs to the bottom gates
Lock 19E: Leakage and masonry repairs
Lock 26E: Canal drained above Lock to carry out culvert works
Lock 28E: Polyurethane resin injection to seal the Lock leakage
Tail Goit Culvert above Lock 28E: Repairs to the culvert, by-wash and towpath
Lock 38E: Replacement of both top and bottom gates, masonry repairs and Polyurethane resin injection to seal the Lock leakage
Lock 39E: Polyurethane resin injection to seal the Lock leakage